Blackpool Football Club
East Stand replacement and redevelopment at Bloomfield Road
| Client | Blackpool Football Club |
|---|---|
| Scope | East Stand development and ongoing modernisations |
East stand replacement and redevelopment
Blackpool FC needed to replace its East Stand fast, to boost capacity following the club’s promotion to the Premier League. Cash flow at the club was slender and time constraints even tighter; with the project posing the added challenge of a 1.8m ground-level variance.
Stadia by GL events delivered the entire project, from initial design to final fit-out, in just eight weeks; on time and within budget. The existing facility was demolished and removed, before construction began on a steelwork stand, with cladding to the roof and rear elevation, supported on 120 steel piles – which were driven to a depth of 22m and encased in concrete. Seating was installed for 5,070 spectators, with a camera platform and more than 100 media positions. The design was scalable, giving Blackpool FC the option to add capacity, reconfigure and develop the structure quickly and easily in the future, and that’s exactly what they did in 2025…
Phase 1: East Stand modernisation (May – August 2025)
The East Stand, which originally delivered by GL events in 2010 benefited from significant programme of modernisation works designed to enhance spectator facilities and improve broadcast infrastructure. This included:
• Replacement of seating risers and seating throughout the stand
• Installation of new spectator seating
• Construction of a new camera platform suspended from the underside of the roof above the front six rows
• Introduction of new supporting steelwork to improve circulation space and pave the way for future development of concourse facilities, toilets and concessions.
The works had to be delivered within the close season while maintaining the integrity of the existing structure and preparing the stand for future phases of redevelopment, planned for 2026. Structural alterations beneath the seating deck required careful engineering to create clear open areas without impacting spectator accommodation above.
Phase 2: Roof and floodlighting upgrade (June – August 2026)
Building on the success of the 2025 works, Blackpool FC commissioned a further phase focused on upgrading the roof structure, replacing ageing components and improving the stadium’s floodlighting provision. The existing roof-mounted floodlighting gantry and support structures were removed and replaced with a modern integrated roofline lighting system. The new arrangement positions floodlights along the front edge of the stand roof, improving aesthetics, simplifying maintenance access and delivering a cleaner stadium profile. The scope of works also included:
• Replacement of roof purlins
• Replacement of roof cladding and gutter systems
• Infill of rear horizontal cladding, extending enclosure from 9m to 12m height across the rear elevation of the stand
Let's Talk About Your Project
Whether you need replacement seating, a new stand, or expert guidance, our team is ready to help you find the right solution.